THE Metropolitan Manila Development Authority (MMDA) has proposed the construction of rainwater impounding facilities inside Camp Aguinaldo to ease recurring flooding on EDSA, with the proposed design released on Wednesday, Aug. 27.
The plan requires detention ponds that will temporarily store excess rainwater during downpours and gradually release it into the EDSA drainage system, leading to the Makiling Creek.
As proposed, the project will be implemented in three phases, covering 182 hectares and involving a golf course near Gate 2, another near Gates 3 and 4, and an open space near Gate 6.

For the first phase near Gate 2, the detention pond has a 361-meter perimeter, a 4,650-square-meter area, an 8-meter depth, and a 37,200-cubic-meter capacity, designed for a 25-year return period (15.6 mm per hour over 24 hours), exceeding the needed 36,945 cubic meters., This news data comes from:http://771bg.com
MMDA proposes rainwater facilities in Camp Aguinaldo to mitigate EDSA flooding
MMDA’s schematic shows that under normal weather, the water bypasses the pond and flows through the lagoon to EDSA.
MMDA proposes rainwater facilities in Camp Aguinaldo to mitigate EDSA flooding
During heavy rain, floodgates divert water flow into the pond; after rain, pumps discharge stored water slowly into EDSA toward the Makiling Creek.
The scope of works covers the impounding area, operations and powerhouse, drainage and electromechanical works, and landscaping and golf course restoration, with a treatment facility under consideration.
Officials said operations and maintenance arrangements, and a memorandum of agreement, are still under discussion.
- Scramble for survivors as Afghan earthquake death toll passes 1,400
- Sen. Pangilinan Advocates for Credit-Worthy Farmers to Boost Agriculture Sector
- Guyana votes amid oil boom, Venezuela tensions
- ₱1.7M shabu seized in Taguig buy-bust
- Marcos declares holidays for 2026
- Appointments panel holds first session
- President asks governor to expose irregularities in govt projects
- House committee subpoenas Sarah Discaya, 4 other contractors over flood control project anomalies
- Gasoline, diesel prices to increase by P1 next week
- Thousands rally in Serbia and accuse police of brutality at anti-government demonstrations